  Start Finish Weather  TSP Concentration  Action Level Limit Level Site Conditions / Mean Temperature  Mean Wind Speed Sampler Filter
Date Time Time   (µg/m3) (µg/m3) (µg/m3) Observations / Remarks (°C) (km/h) ID ID
05-Sep-11 11:08 12:08 Fine 88 322 500 Dust from Project site, traffic emission and  dust from other construction sites 29.2 6.0 A005-12a -
12:08 13:08 Fine 89
13:08 14:08 Fine 88
11-Sep-11 13:21 14:21 Cloudy 80 322 500 Dust from Project site, traffic emission and  dust from other construction sites 28.2 11.5 A005-13a -
14:21 15:21 Cloudy 82
15:21 16:21 Cloudy 85
17-Sep-11 12:43 13:43 Sunny 82 322 500 Dust from Project site, traffic emission and  dust from other construction sites 29.4 7.4 A005-11a -
13:43 14:43 Sunny 83
14:43 15:43 Sunny 83
23-Sep-11 13:11 14:11 Cloudy 81 322 500 Dust from Project site, traffic emission and  dust from other construction sites 25.6 6.2 A005-08a -
14:11 15:11 Cloudy 82
15:11 16:11 Cloudy 80
30-Sep-11# 14:35 15:35 Fine 76 322 500 Dust from Project site, traffic emission and  dust from other construction sites 27.7 13.8 A005-12a -
15:35 16:35 Fine 78
16:35 17:35 Fine 80
      Min. 76              
      Max. 89              
      Average 82              
                       
# The proposed 1-hr TSP Monitoring on 29 September 2011 was re-scheduled to 30 September 2011 due to adverse weather .